Firm-Fill High Strength

Firm-Fill High Strength
From sprawling malls to sky-scraping
office buildings, Firm-Fill High Strength resurfaces any cracked or
damaged concrete to better than new.
From birdbaths to leveling an entire
floor, from 600 to 40,000 sq. ft. (56 to 3716 sq. m) installed per
day, from feather edge to 3 1/2 inches (89 mm) deep, Firm-Fill High
Strength is the economical solution to correct your concrete problems.
With surface hardness superior to its
competition, Firm-Fill High Strength provides a durable, flat floor
for virtually any finished floor goods including hardwood floors,
ceramic tile, carpet and pad, glued down carpet and vinyl.
- 2250 to over 3000 P.S.I (approx.
15.5 to 20.7 MPa)
- New Construction or Renovation
- Strong, Smooth Surface
- Over 50 UL Ratings
- Superior Bonding Qualities
- Superior Crack Resistance
- Environmentally Safe
- Consistent Quality
- Trained, Licensed Applicators
PART I
GENERAL
1.1 Scope -
Specify to meet project requirements
A. Work
included:
- Firm-Fill
High Strength
- Hacker
Floor Sealer & Primer
1.2 Qualifications
A. Firm-Fill
High Strength must be installed by Licensed Applicators of Hacker
Industries, Inc., using approved mixing and pumping equipment.
B. Firm-Fill High Strength shall be delivered in original,
unopened bags and protected from exposure to the elements after
deliver.
C. Install before or after drywall.
D. Before, during, and after installation of Firm-Fill High
Strength, the building interior must be ventilated and heated to a
minimum of 50 F (approx. 10 C)
E. All materials specified herein shall be approved by Hacker
Industries, Inc.
PART II
PRODUCTS
2.1 Materials
A. Gypsum
Concrete - Firm-Fill High Strength as manufactured by Hacker
Industries, Inc.
B. Hacker Floor Primer and Sealer C. Sand: 1/8" (approx. 3mm)
or less washed plaster or mortar sand.
D. Water: Portable and free from impurities.
PART III
EXECUTION
3.1 Condition
of Subfloor
A. General
Contractor is responsible for providing a structurally sound
(L/360) subfloor, broom cleaned, and free of oil, grease or other
contaminants.
B. All cracks and voids should be filled with a quick-setting
taping compound to prevent leaking.
C. Before installation, General Contractor shall inspect and
approve the condition of the subfloor.
3.2 Preparation
of Subfloor
A. Priming:
Prime concrete subfloors using Hacker Primer and/or Sealer.
B. Prepare subfloor meeting requirements of Hacker Renovation
Specifications.
3.3 Mixing
Instructions
A. 5 to 7
gallons (approx. 22.7 to 26.5 liters) of water and sand as
specified per 80 pound (approx. 36.3 kg) bag of Firm-Fill High
Strength, Do not over water Water amount will change with wetness
of sand.
B. Firm-Fill High Strength mix proportions and methods shall be in
strict accordance with Hacker recommendations. Firm-Fill High
Strength is available in two mixing designs:
- 2250-2500
P.S.I. (approx. 15.5 to 17.8MPa) - 1.9 cubic feet (approx.
.054 cu.m) of sand per 80 lb. (approx. 36.3 kg) bag of
Firm-Fill High Strength.
- 2500-3000
P.S.I (approx. 17.2 to 20.7 MPa) - 1.4 cubic feet (approx.
.040 cu.m) of sand per 80 lb. (approx. 36.3 kg) bag of
Firm-Fill High Strength.
3.4 Underlayment
Application
A. The
minimum thickness of Firm-Fill High Strength varies with the type
of floor system. Firm-Fill High Strength can be feather edged over
all concrete substrates. Firm-Fill High Strength may be installed
at a minimum depth of 1 1/2" (approx. 38mm) over extruded or
expanded polystrene. The concrete slab must be 28 days or older
and clean of grease or other contaminants.
B. Protection: After installation, temporary wood planking should
be placed wherever the underlayment will be subject to heavy
wheeled or concentrated loads.
C. Drying: Prior to the installation of finished floor goods, the
Firm-Fill High Strength must be free from any moisture. The
General Contractor shall provide continuous ventilation and
adequate heat to rapidly remove moisture from the area until the
underlayment is dry. General Contractor should consult flooring
contractor for recommended procedures to test for dryness.
D. Firm-Fill High Strength is suitable for interior applications
only and must be covered by a finished floor material.
3.5 Field
Quality Control
A. Slump
Test - Firm-Fill High Strength shall be tested for slump as it is
being installed using a 2" by 4" (approx. 51 mm by 102
mm) cylinder. The patty size should be 7 1/2" (approx. 191
mm) plus or minus 1/2" (approx. 13 mm) in diameter.
B. Field Samples - Testing of molded cube samples shall be in
accordance with ASTM: C472 using split brass molds. Prior to
independent sampling, contact Hacker Industries, Inc., to insure
proper ASTM methods are followed. Test results shall be available
from the applicator upon request.
Return to the Pro-Crete